Welcome to Alcon!

  • About us

    Who is Alcon?

    EPC Contractor in the Upstream, Midstream, Downstream, Power Systems and Infrastructure for projects with individual value of up to 250 MUSD. P&C Contractor for projects up to 400M USD.

     

     

    Alcon's Read More

  • Alcon News

    Alcon's most recent news! Read More
  • Under Execution Projects

    Alcon's current projects:
    Akia Phase II
    PH Monorail
    Nun River Project
    Soku Project
    Okoloma Project
    Bonny RA Project
    Forcado Yokri Project
    Read More
  • Finalized Projects

    A brief presentation of major Alcon's executed projects. Read More
  • CSR

    CORPORATE SOCIAL RESPONSIBILITY (CSR) POLICY

    ALCON  believe the principles of corporate social responsibility (CSR) and good corporate citizenship are key to our success. Our CSR stance focuses on four key areas : Client and marketplace

    Read More
  • 1
  • 2
  • 3
  • 4
  • 5

Akwa Ibom International Airport (PHASE 1)

SCOPE OF WORK

Construction of Akwa Ibom State International Airport -includes Domestic Terminal, Control Tower, Fire Service and Utility Buildings including NAVAIDS, METAIDS, Access Roads, Water, Fire and Sewage Systems.

 

CLIENT AKWA IBOM STATE GOVERNMENT
Project Description Akwa Ibom International Airport (PHASE 1)
Construction of Akwa Ibom State International Airport - includes Domestic Terminal, Control Tower, Fire Service and Utility Buildings including NAVAIDS, METAIDS, Access Roads, Water, Fire and Sewage Systems.
Year Executed 2010
Total Amount (USD) $100,000,000
Status COMPLETED

 

Details EPC for FLB Gbaran Project

Contract No.:
E-17705

Client:
SPDC / SAIPEM

Award Date:
aprile 2006

Mobilization Date:
settembre 2006

Demobilization Date:
ottobre 2006

Actual Progress:
100%

EPC for FLB Gbaran Project

Scope of work:

Construction of 144 units Accommodation including associated facilities not limited to: Security Building, Switch Rooms, Material Yards, Telecommunications Fire Station, Waste Compaction, Effluent Treatment, CPF Control Room, Fire Water Pumping Station, Diesel Pumping Station, Medical Centre, Production / Maintenance, Utility Building & Mess/Recreation/Laundry.

Okoloma Gas Plant & Pipelines

Scope of work:

  1. Construction of a new 240 MMscf/d gas plant based on the LTS process. The gas plant will consist of a 240 MMscf/d JT-LTS High pressure train and a 120 MMscf/d Twister-LTS Low Pressure train, condensate stabilization with off-gas compression, metering, storage and export facilities.

 

  1. Installation of a :
  • new Afam Field NAG Manifold and 5nos. 8" flowlines
  • 12" x 10.6km NAG bulkline.
  • 6" x 3.0km oil.
  • 8" x 1.2 km NAG flowline.
  • 2 nos 8" x 6.4 km NAG flowlines
  • 16" x 2.0 km sales gas line
  • 18"/8" x 11.7 km condensate evacuation pipeline (pipe in pipe).
  • 4" x 2.0 km condensate return line
  • 12" x 2.0 km water drain line (GRE)
  • 12" x 1.6 km sales gas export.

EPIC for Idu Field Gas Recovery and Plant Revamping Project (Phase I)

Scope of work:

Revamping of the existing flowstation and construction of a 150 MMscf/d gas plant including installation of the following main items:

  1. NAG separator , Launching trap, Metering unit, Gas boot
  2. Flare and blow-down system
  3. LP Gas compression packages, MP Gas compression package, Turbo-generators packages
  4. Fuel gas system, Diesel oil system
  5. Air compression unit
  6. Emergency diesel generators
  7. Water well system, Potable water System, Water treatment
  8. Nitrogen generator package
  9. Fire Fighting system
  10. 12' oil trunk (600m) line to Brass pipeline tie-in
  11. OB/OB gas plant: Receiving trap, slug catcher, pipeline, instrumentation, electrical, civil
  12. Electric transformers, M.V. switchboard, MCC and PMCC panels
  13. DCP, ASP, DCS, ESD,PSD, F&G systems and ECD